Turbocharger
Part name
Tightening torque
1: 52 N・m { 5.3 kgf・m / 38 lb・ft }
4: 25 N・m { 2.5 kgf・m / 18 lb・ft }
6: 10.0 N・m { 1.0 kgf・m / 89 lb・in }
8: 10.0 N・m { 1.0 kgf・m / 89 lb・in }
10: 25 N・m { 2.5 kgf・m / 18 lb・ft }
11: 23 N・m { 2.3 kgf・m / 17 lb・ft }
12: 51 N・m { 5.2 kgf・m / 38 lb・ft }
13: 52 N・m { 5.3 kgf・m / 38 lb・ft }
15: 51 N・m { 5.2 kgf・m / 38 lb・ft }
16: 25 N・m { 2.5 kgf・m / 18 lb・ft }
17: 51 N・m { 5.2 kgf・m / 38 lb・ft }
1) Perform the following procedures before installing the turbocharger.
2) After installing the turbocharger, warm up the engine at idle.
Caution
1) Feed 1 cc (approximately 20 drops) of engine oil into the oil feed port.
Legend
2) Install the turbocharger oil pipe and gasket to the turbocharger.
Caution
Tightening torque: 10.0 N・m { 1.0 kgf・m / 89 lb・in }
Legend
3) Install the water feed and return pipe, as well as the gasket to the turbocharger.
Caution
Tightening torque: 10.0 N・m { 1.0 kgf・m / 89 lb・in }
4) Install the following parts as a set to the exhaust manifold.
Caution
Tightening torque: 52 N・m { 5.3 kgf・m / 38 lb・ft }
5) Connect the connector to the turbocharger.
1) Temporarily tighten the turbocharger upper bracket to the turbocharger and turbocharger lower bracket.
2) Final tighten the turbocharger upper bracket to the turbocharger and turbocharger lower bracket.
Tightening torque: 51 N・m { 5.2 kgf・m / 38 lb・ft }
1) Connect the turbocharger oil pipe to the oil cooler and crankcase.
Caution
Tightening torque: 25 N・m { 2.5 kgf・m / 18 lb・ft } Crankcase side
Tightening torque: 23 N・m { 2.3 kgf・m / 17 lb・ft } Oil cooler side
Legend
1) Connect the turbocharger water return hose to the water feed and return pipe.
2) Connect the turbocharger water feed hose to the water feed and return pipe.
Legend
1) Install the intake hose to the intercooler and turbocharger.
Caution
Tightening torque: 5.0 N・m { 0.5 kgf・m / 44 lb・in }
Legend