CHARCOAL CANISTER INSPECTION [LF, L5]


id0116a7800500


Airflow Inspection

1.  Remove the charcoal canister. (See CHARCOAL CANISTER REMOVAL/INSTALLATION [LF, L5].)

2.  Perform the following procedures:

•  Assemble the hose used for inspection (bore: approx. 14.8 mm {0.58 in}) to port A.
•  Cover ports B and C with the caps.
am3zzw00005418
Caution
•  Do not apply a pressure 20 kPa {150 mmHg, 5.91 inHg} or more to the charcoal canister for 1 min. or more. Doing so will damage the charcoal canister.

3.  Apply pressure (19.6 kPa {147 mmHg, 5.79 inHg}) through the hose, and verify that air does not leak from the charcoal canister.

am3zzw00005419

•  If there is airflow, replace the charcoal canister. (See CHARCOAL CANISTER REMOVAL/INSTALLATION [LF, L5].)