OIL CONTROL VALVE (OCV) INSPECTION[L3 Turbo]
id0110b3801400
Coil Resistance Inspection
1. Remove the battery cover.
2. Disconnect the negative battery cable.
3. Disconnect the OCV connector.
4. Measure the coil resistance between terminals A and B using a tester.
am3zzw00003523
|
5. Connect the OCV connector.
6. Connect the negative battery cable.
7. Install the battery cover.
Spool Valve Operation Inspection
1. Remove the battery cover.
2. Disconnect the negative battery cable.
3. Disconnect the OCV connector.
4. Remove the OCV. (See OIL CONTROL VALVE (OCV) REMOVAL/INSTALLATION[L3 Turbo].)
5. Verify that the spool valve in the OCV is in the maximum valve timing retard position as indicated in the figure.
acxuuw00000140
|
6. Verify that the battery is fully charged.
7. Apply battery positive voltage between the OCV terminals and verify that the spool valve operates and moves to the maximum valve timing advance position.
am3zzw00003523
|
acxuuw00000142
|
8. Stop applying battery positive voltage and verify that the spool valve returns to the maximum valve timing retard position.
9. Connect the OCV connector.
10. Connect the negative battery cable.
11. Install the battery cover.