SUNROOF MOTOR INSPECTION
id091500801100
1. Measure the voltage at each terminal (other than terminal G).
2. Disconnect the negative battery cable.
3. Verify that continuity at terminal G is as indicated in the Terminal Voltage Table (Reference).
4. If the parts and wiring harnesses are normal but the system still does not work properly, replace the sunroof relay.
Terminal voltage table (Reference)
am3zzw00002324
|
Terminal |
Signal |
Connected to |
Test condition |
Voltage (V)/Continuity |
Inspection item |
---|---|---|---|---|---|
A
|
Slide open
|
Sunroof switch
|
Sunroof is fully opening.
|
B+
|
Sunroof switch (See SUNROOF SWITCH INSPECTION.)
|
Other
|
0
|
||||
B
|
Slide close/tilt down
|
Sunroof switch
|
Sunroof is closing/tilting down.
|
B+
|
Sunroof switch (See SUNROOF SWITCH INSPECTION.)
|
Other
|
0
|
||||
C
|
Tilt up
|
Sunroof switch
|
Sunroof is tilting up.
|
B+
|
Sunroof switch (See SUNROOF SWITCH INSPECTION.)
|
Other
|
0
|
||||
E
|
IG2
|
SUNROOF 7.5 A fuse
|
Turn the ignition switch to the ON position.
|
B+
|
SUNROOF 7.5 A fuse
|
G
|
GND
|
GND
|
Under any condition: Check for continuity to ground.
|
Continuity
|
GND
|
J
|
Power supply
|
SUNROOF 20 A fuse
|
Under any condition
|
B+
|
SUNROOF 20 A fuse
|