VALVE CLEARANCE INSPECTION [MZR 1.6]


id0110f6803400

1.  Disconnect the negative battery cable. (See NEGATIVE BATTERY CABLE DISCONNECTION/CONNECTION [MZR 1.6].)

2.  Remove the front splash shield No.1 (RH). (See SPLASH SHIELD REMOVAL/INSTALLATION.)

3.  Remove the ignition coils. (See IGNITION COIL REMOVAL/INSTALLATION [MZR 1.6].)

4.  Set the wiring harness aside.

5.  Remove the cylinder head cover. (See TIMING CHAIN REMOVAL/INSTALLATION [MZR 1.6].)

6.  Measure the valve clearance.

Note
•  Make sure to note down the measured values for choosing the suitable replacement tappets.
(1)  Rotate the crankshaft clockwise so that the No.1 cylinder is at TDC of the compression stroke.
(2)  Measure the valve clearance at A in the figure.
am2zzw00000092
•  If not within specification, replace the tappet and adjust the valve clearance to the median value. (See VALVE CLEARANCE ADJUSTMENT [MZR 1.6].)
Valve clearance [Engine cold]
IN: 0.27—0.33 mm {0.0107—0.0129 in}
EX: 0.27—0.33 mm {0.0107—0.0129 in}
(3)  Rotate the crankshaft clockwise 360° so that the No.4 cylinder is at TDC of the compression stroke.
(4)  Measure the valve clearance at B in the figure.
am2zzw00000092
•  If not within specification, replace the tappet and adjust the valve clearance to the median value. (See VALVE CLEARANCE ADJUSTMENT [MZR 1.6].)
Valve clearance [Engine cold]
IN: 0.27—0.33 mm {0.0107—0.0129 in}
EX: 0.27—0.33 mm {0.0107—0.0129 in}

7.  Install in the reverse order of removal.