VALVE CLEARANCE INSPECTION [MZR 1.6]
id0110f6803400
1. Disconnect the negative battery cable. (See NEGATIVE BATTERY CABLE DISCONNECTION/CONNECTION [MZR 1.6].)
2. Remove the splash shield (RH). (See SPLASH SHIELD REMOVAL/INSTALLATION.)
3. Remove the ignition coils. (See IGNITION COIL REMOVAL/INSTALLATION [MZR 1.6].)
4. Set the wiring harness aside.
5. Remove the cylinder head cover. (See TIMING CHAIN REMOVAL/INSTALLATION [MZR 1.6].)
6. Measure the valve clearance.
-
Note
-
• Make sure to note down the measured values for choosing the suitable replacement tappets.
- (1) Rotate the crankshaft clockwise so that the No.1 cylinder is at TDC of the compression stroke.
-
- (2) Measure the valve clearance at A in the figure.
-
-
-
Valve clearance [Engine cold]
-
IN: 0.27—0.33 mm {0.0107—0.0129 in}
EX: 0.27—0.33 mm {0.0107—0.0129 in}
- (3) Rotate the crankshaft clockwise 360° so that the No.4 cylinder is at TDC of the compression stroke.
-
- (4) Measure the valve clearance at B in the figure.
-
-
-
Valve clearance [Engine cold]
-
IN: 0.27—0.33 mm {0.0107—0.0129 in}
EX: 0.27—0.33 mm {0.0107—0.0129 in}
7. Install in the reverse order of removal.