| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
| Replace |
| Add Following Operations If Performed With Piston & Ring Jobs |
| Main Bearings, Renew | 1.0 | 0.0 | A | Add The Following Operations If Performed Along With "Piston & Ring" Jobs. |
| Crankshaft, Renew | 4.6 | 0.0 | A | Does Not Include: R&R Engine. |
| Oil Pump, Renew | 0.5 | 0.0 | A | Does Not Include: R&R Engine. |
| Oil Pump Screen, Clean | 0.2 | 0.0 | A | Does Not Include: R&R Engine. |
| Timing Chain, Renew | 1.2 | 0.0 | A | Does Not Include: R&R Engine. |
| Tune-Up | 0.6 | 0.0 | A | See Valves Grind Head Removed & Combinations |
| One CYL |
| Right Bank | 8.3 | 6.3 | A | Includes: R&R Cylinder Head, Oil Pan, Hone Cylinders And Plastigage Bearings. |
| Left Bank | 8.2 | 6.2 | A | Includes: R&R Cylinder Head, Oil Pan, Hone Cylinders And Plastigage Bearings. |
| Both Banks | 12.1 | 9.1 | A | Includes: R&R Cylinder Head, Oil Pan, Hone Cylinders And Plastigage Bearings. |
| Note |
| With AC, Add | 0.5 | 0.3 | |