Piston: Labor Times
| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes | |
| Replace | ||||
| Note | ||||
| To Grind Valves, Add | 3.8 | 2.7 | A | |
| With Folding Top, Add | 0.7 | 0.4 | A | |
| Add Following Operations If Performed With Piston & Ring Jobs | ||||
| Camshaft, Renew | 5.8 | 0.0 | A | |
| Main Bearing, Renew | 1.5 | 0.0 | A | |
| Crankshaft, Renew | 6.8 | 0.0 | A | |
| Oil Pump, Renew | 0.9 | 0.0 | A | |
| Oil Pump Screen, Clean | 0.2 | 0.0 | A | |
| Timing Chain, Renew | 1.9 | 0.0 | A | |
| Valve Lifters, Renew | ||||
| Right Bank | 3.0 | 0.0 | A | |
| Left Bank | 2.7 | 0.0 | A | |
| Both Banks | 3.4 | 0.0 | A | |
| Tune-Up | 0.8 | 0.0 | A | |
| Rear Main Seal, Renew | ||||
| Manual Trans | 2.0 | 0.0 | A | |
| Auto Trans | 1.5 | 0.0 | A | |
| One CYL | ||||
| Right Bank | 15.1 | 10.8 | A | |
| Left Bank | 13.2 | 9.4 | A | |
| Both Banks | 19.7 | 14.1 | A | |
| All Cyls | ||||
| Right Bank | 18.1 | 12.9 | A | |
| Left Bank | 16.1 | 11.5 | A | |
| Both Banks | 25.2 | 18.0 | A | |
| Each Additional | 1.0 | 0.7 | A |