Removal Procedure
1. Remove the transmission filter.
2. Remove the 1-2 accumulator, if necessary.
Important: Removal of the 1-2 accumulator is necessary only if servicing the pressure control solenoid.
3. Disconnect the internal wiring harness electrical connectors from the following components:
^ Transmission fluid pressure switch (1)
^ 1-2 shift control solenoid (2)
^ 2-3 shift control solenoid (3)
^ Pressure control solenoid (4)
^ torque converter clutch pulse width modulation (TCC PWM) solenoid (5)
^ 3-2 control solenoid (6)
4. Remove the pressure control solenoid retainer bolt (364A) and retainer (378).
5. Remove the pressure control solenoid (377).
6. Remove the 1-2 shift solenoid retainer (395) and the 1-2 shift solenoid (267A).
7. Remove the 2-3 shift solenoid retainer (395) and the 2-3 shift solenoid (367A).
8. Remove the 3-2 control solenoid retainer (395) and the 3-2 control solenoid (394).
Installation Procedure
1. Install the 3-2 control solenoid (394) and the 3-2 control solenoid retainer (395).
2. Install the 2-3 shift solenoid (367A) and the 2-3 shift solenoid retainer (395).
3. Install the 1-2 shift solenoid (267A) and the 1-2 shift solenoid retainer (395).
4. Install the pressure control solenoid (377).
Important: When installing the pressure control solenoid, the electrical connector (2) must be in the position shown.
5. Install the pressure control solenoid retainer (378) and retainer bolt (364A).
^ Tighten the bolt to 11 Nm (97 inch lbs.).
Notice: Refer to Fastener Notice in Service Precautions.
6. Connect the internal wiring harness electrical connectors to the following components:
^ Transmission fluid pressure switch (1)
^ 1-2 shift control solenoid (2)
^ 2-3 shift control solenoid (3)
^ Pressure control solenoid (4)
^ TCC PWM solenoid (5)
^ 3-2 control solenoid (6)
7. Install the 1-2 accumulator, if necessary.
8. Install the transmission filter.