Charging System Preliminary Inspection
CHARGING SYSTEM PRELIMINARY INSPECTION
Inspection Procedure
1.CHECK BATTERY TERMINALS CONNECTION
Check if battery terminals are clean and tight.
Is the inspection result normal?
YES - GO TO 2.
NO - Repair battery terminals connection.
2.CHECK FUSE
Check for blown fuse and fusible link.
Is the inspection result normal?
YES - GO TO 3.
NO - Be sure to eliminate cause of malfunction before installing new fuse or fusible link.
3.CHECK GENERATOR GROUND TERMINAL CONNECTION
Verify connector E206 terminal 5 (generator ground harness) is clean and tight.
Is the inspection result normal?
YES - GO TO 4.
NO - Repair connection.
4.CHECK DRIVE BELT TENSION
Check drive belt tension. Procedures.
Is the inspection result normal?
YES - Inspection End.
NO - Repair as needed.