Operation CHARM: Car repair manuals for everyone.
Manuals through 2025 now available!

Our trusted friends have launched a new website named LEMON, which has newer manuals. It also contains all the CHARM manuals.

LEMON is the spiritual successor to CHARM, I recommend you try it!

Link: lemon-manuals.la or lemon-manuals.org.ua

(Some people have issue connecting. LEMON is investigating. For now, use Firefox or change your DNS server)

Or, hide this message: temporarily or permanently

General Module: Testing and Inspection


Inspection





Connector A
1. Remove the CPU from the joint box.
2. Measure the voltage at the CPU terminals from the joint box side, referring to the terminal voltage list below.
3. If not as specified, inspect the parts listed under "Inspection area" and the related wiring harnesses.
4. If the parts and wiring harnesses are OK but the system still does not work properly, replace the CPU.





Connector B
1. Follow the appropriate procedure, referring to the terminal voltage list below.

Terminals 2H (MX-6 only), 2N, and 2T
1. Disconnect the CPU connector.
2. Check for continuity between the terminals of the CPU connector and ground.





Terminals except 2H (MX-6 only), 2N, and 2T
1. Reconnect the CPU connector.
2. Install the CPU onto the joint box.
3. Measure the voltage at the CPU terminals.

2. If not as specified, inspect the parts listed under "Inspection area" and the related wiring harnesses.
3. If the parts and wiring harnesses are OK but the system still does not work properly, replace the CPU.

Terminal Voltage: