Ignition Lock Solenoid: Testing and Inspection
SHIFT-LOCK ACTUATOR INSPECTION (GF4A-EL)1. Remove the rear console box and center panel.
2. Shift the selector lever to P position.
3. Turn the ignition switch to ON (engine is off) , and check for terminal voltage and continuity, referring to the chart. When checking for continuity between terminal h (harness side) and ground, disconnect the connector.
4. If not as specified, repair the wire harness and/or replace the shift-lock actuator.
5. Install the center panel and rear console box.
6. Verify correct operation of the shift-lock system.