OIL CONTROL VALVE (OCV) INSPECTION [MZR 2.0, MZR 2.5]
id011006801400
Coil Resistance Inspection
1. Remove the battery cover. (See BATTERY REMOVAL/INSTALLATION [MZR 2.0, MZR 2.5].)
2. Disconnect the negative battery cable. (See BATTERY REMOVAL/INSTALLATION [MZR 2.0, MZR 2.5].)
3. Remove the plug hole plate. (See PLUG HOLE PLATE REMOVAL/INSTALLATION [MZR 2.0, MZR 2.5].)
4. Disconnect the OCV connector.
5. Measure the resistance between terminals A and B using an ohmmeter.
am6zzw00001789
|
6. Install in the reverse order of removal.
Spool Valve Operation Inspection
1. Remove the OCV. (See OIL CONTROL VALVE (OCV) REMOVAL/INSTALLATION [MZR 2.0, MZR 2.5].)
2. Verify that the spool valve in the OCV is in the minimum valve timing retard position as indicated in the figure.
am3zzw00011676
|
3. Verify that the battery is fully charged. (See BATTERY INSPECTION [MZR 2.0, MZR 2.5].)
am6zzw00001789
|
4. Apply battery positive voltage between the OCV terminals and verify that the spool valve operates and moves to the maximum valve timing advance position.
am3zzw00006869
|
5. Stop applying battery positive voltage and verify that the spool valve returns to the minimum valve timing retard position.
6. Install the OCV. (See OIL CONTROL VALVE (OCV) REMOVAL/INSTALLATION [MZR 2.0, MZR 2.5].)