GENERATOR CONSTRUCTION [13B-MSP]


id0117f2102300

•  With the elimination of the voltage regulator, generator control is carried out by the PCM. Excitation current in the field coil is increased or decreased by the duty signal from the PCM sent to the power transistor built into the generator. (See GENERATOR CONTROL OPERATION [13B-MSP].)
ar8wzn00000358
ar8wzn00000359
•  If there is malfunction in the charging system, the generator warning light in the instrument cluster illuminates. (See ON-BOARD DIAGNOSTIC SYSTEM TEST MODE [13B-MSP].)