Power Distribution
POWER DISTRIBUTION: INTEGRATION RELAY: INSTALLATION
1. INSTALL NO. 1 INTEGRATION RELAY
(a) Connect the 3 connectors.
(b) Engage the 2 claws to install the No. 1 integration relay as shown in the illustration.
2. INSTALL NO. 1 RELAY BLOCK COVER
(a) Engage the 3 claws to install the No. 1 relay block cover.
3. CONNECT CABLE TO AUXILIARY BATTERY NEGATIVE TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.
4. INSTALL DECK FLOOR BOX RH Installation
5. INSTALL REAR NO. 3 FLOOR BOARD Installation
6. INSTALL REAR NO. 2 FLOOR BOARD Installation