Installation
2GR-FE CHARGING: GENERATOR: INSTALLATION
INSTALLATION
1. INSTALL GENERATOR ASSEMBLY
(a) Install the wire harness clamp stay.
Torque: 8.4 Nm (86 kgf-cm, 74in-lbf)
(b) Install the generator bracket with the nut.
Torque: 20 Nm (204 kgf-cm, 15ft-lbf)
(c) Connect the wire harness clamp.
(d) Install the generator assembly with the bolt.
Torque: 20 Nm (204 kgf-cm, 15ft-lbf)
(e) Install the 2 bolts.
Torque: 43 Nm (438 kgf-cm, 32ft-lbf)
(f) Connect the generator connector to the generator assembly.
(g) Install the generator wire with the nut.
Torque: 9.8 Nm (100 kgf-cm, 87in-lbf)
(h) Install the terminal cap.
(i) Connect the 2 wire harness clamps.
(j) Connect the magnetic clutch connector to the compressor and magnetic clutch.
2. INSTALL V-RIBBED BELT Installation
3. INSTALL FAN SHROUD Installation
4. INSTALL UPPER RADIATOR SUPPORT SUB-ASSEMBLY Installation
5. INSTALL HOOD LOCK ASSEMBLY Installation
6. INSTALL HOOD LOCK CONTROL CABLE COVER Installation
7. CONNECT RADIATOR RESERVOIR TANK HOSE Installation
8. INSTALL NO. 1 AIR CLEANER INLET Installation
9. INSTALL AIR CLEANER CASE SUB-ASSEMBLY Installation
10. INSTALL AIR CLEANER FILTER ELEMENT
11. INSTALL AIR CLEANER CAP SUB-ASSEMBLY Installation
12. INSTALL NO. 2 AIR CLEANER INLET Installation
13. INSTALL ENGINE ROOM COVER SIDE Installation
14. INSTALL COOL AIR INTAKE DUCT SEAL Installation
15. INSTALL V-BANK COVER SUB-ASSEMBLY Installation
16. INSTALL FRONT FENDER APRON SEAL RH
17. INSTALL FRONT FENDER SPLASH SHIELD SUB-ASSEMBLY RH
18. INSTALL NO. 1 ENGINE UNDER COVER
19. INSTALL FRONT WHEEL RH
Torque: 103 Nm (1,050 kgf-cm, 76ft-lbf)
20. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL Installation
21. PERFORM INITIALIZATION
(a) Perform initialization procedure Repair Instruction - Initialization.
HINT: Some vehicle systems require initialization after reconnecting the cable to the negative battery terminal.