Pinpoint Test B: The Shift Control Is Out of Correct Gear Relationship
External Controls - Column Shift
Pinpoint Tests
PINPOINT TEST B: THE SHIFT CONTROL IS OUT OF CORRECT GEAR RELATIONSHIP
-------------------------------------------------
B1 CHECK THE SHIFT CONTROL LINKAGE
- Apply the brake pedal.
- Gain access to the column shift control linkage.
- Position the selector lever in all ranges.
- Observe all linkages during operation.
- Is the linkage damaged?
Yes
INSTALL a new column shift control linkage. TEST the system for normal operation.
No
GO to B2.
-------------------------------------------------
B2 CHECK THE SELECTOR LEVER CABLE
- Check selector lever cable and bracket for installation and tightness.
- Is the selector lever cable correctly installed and adjusted?
Yes
VERIFY the selector lever cable adjustment. REFER to Selector Lever Cable Adjustment Adjustments. ADJUST the selector lever cable if necessary. GO to B3 .
No
REPAIR as necessary. TEST the system for normal operation.
-------------------------------------------------
B3 CHECK THE LINKAGE/CABLE FOR CORRECT GEAR RELATIONSHIP
- Apply the brake pedal.
- Position the selector lever in all ranges.
- Does the indicator match the gear selection?
Yes
System OK. TEST the system for normal operation.
No
REFER to Instrument Panel, Gauges and Warning Indicators.
-------------------------------------------------