VALVE CLEARANCE INSPECTION [ZY, Z6]
id0110b0803400
1. Remove the battery cover. (See BATTERY REMOVAL/INSTALLATION [ZY, Z6].)
2. Disconnect the negative battery cable.
3. Remove the splash shield (RH). (See SPLASH SHIELD REMOVAL/INSTALLATION.)
4. Perform the following procedure.
-
Except European (U.K.) specs.
-
-
European (U.K.) specs.
-
5. Remove the ignition coils. (See IGNITION COIL REMOVAL/INSTALLATION [ZY, Z6].)
6. Set the wiring harness out of the way.
7. Remove the cylinder head cover. (See TIMING CHAIN REMOVAL/INSTALLATION [ZY, Z6].)
8. Measure the valve clearance.
-
Note
-
• Make sure to note down the measured values for choosing the suitable replacement tappets.
- (1) Rotate the crankshaft clockwise so that the No.1 cylinder is at TDC of the compression stroke.
- (2) Measure the valve clearance at A in the figure.
-
-
-
Valve clearance [Engine cold]
-
IN: 0.27—0.33 mm {0.0107—0.0129 in}
EX: 0.27—0.33 mm {0.0107—0.0129 in}
- (3) Rotate the crankshaft clockwise 360° so that the No.4 cylinder is at TDC of the compression stroke.
- (4) Measure the valve clearance at B in the figure.
-
-
-
Valve clearance [Engine cold]
-
IN: 0.27—0.33 mm {0.0107—0.0129 in}
EX: 0.27—0.33 mm {0.0107—0.0129 in}
9. Install in the reverse order of removal.