HV Relay Assembly
HYBRID / BATTERY CONTROL: HV RELAY ASSEMBLY: INSPECTION
1. HYBRID BATTERY JUNCTION BLOCK ASSEMBLY
(a) Inspect SMRB.
(1) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
Text in Illustration
(2) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
(b) Inspect SMRG.
(1) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
Text in Illustration
(2) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
(c) Inspect SMRP.
(1) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
Text in Illustration
(2) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
(d) Inspect CHRB.
(1) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
Text in Illustration
(2) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
(e) Inspect CHRG.
(1) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
Text in Illustration
(2) Measure the resistance according to the value(s) in the table below.
Standard Resistance: