Installation
POWER DISTRIBUTION: POWER MANAGEMENT CONTROL ECU: INSTALLATION
1. INSTALL POWER MANAGEMENT CONTROL ECU
(a) Engage the 2 claws to install the power management control ECU as shown in the illustration.
2. INSTALL ECU INTEGRATION BOX RH
(a) Install the ECU integration box RH with the bolt and 2 nuts.
Bolt - Torque : 8.0 Nm (82 kgf-cm, 71 in-lbf)
Nut - Torque : 5.5 Nm (56 kgf-cm, 49 in-lbf)
(b) Engage the 3 clamps.
(c) Connect each connector.
3. INSTALL GLOVE COMPARTMENT DOOR ASSEMBLY Installation
4. INSTALL NO. 2 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY Installation
5. CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.
6. INSTALL DECK FLOOR BOX RH Installation
7. INSTALL REAR DECK FLOOR BOX Installation
8. INSTALL NO. 1 DECK BOARD Installation
9. INSTALL NO. 2 DECK BOARD Installation
10. INSTALL DECK BOARD ASSEMBLY Installation