Installation
P410 HYBRID TRANSMISSION / TRANSAXLE: GENERATOR CABLE: INSTALLATION
1. INSTALL GENERATOR CABLE
NOTICE:
Wear insulated gloves.
(a) Install the generator cable to the hybrid transaxle assembly with the 3 bolts.
Torque : 10 Nm (102 kgf-cm, 7 ft-lbf)
NOTICE:
Keep the sealing surface of the generator cable and the connector terminal joint free of foreign matter.
(b) Engage the 2 claws to install a new terminal cap.
NOTICE:
When installing the terminal cap to the generator cable terminal block, keep the sealing surface free of foreign matter.
(c) Place the generator cable connector shell in position and install it with the 3 bolts.
Torque : 20 Nm (204 kgf-cm, 15 ft-lbf)
(d) Connect the generator cable clamp to the motor cable bracket.
2. INSTALL RADIATOR PIPE
(a) Install the radiator pipe with the 2 bolts.
Torque : 19 Nm (194 kgf-cm, 14 ft-lbf)
(b) Connect the No. 3 radiator hose, No. 4 water by-pass hose and No. 1 radiator hose with the 3 clamps.
3. INSTALL INVERTER TRAY BRACKET Installation
4. INSTALL INVERTER RESERVE TANK ASSEMBLY Installation
5. INSTALL INVERTER WITH CONVERTER ASSEMBLY Installation
6. CONNECT WATER HOSE Installation
7. CONNECT NO. 2 ENGINE ROOM WIRE Installation
8. REMOVE INVERTER COVER Installation
9. CONNECT NO. 2 ENGINE WIRE Installation
10. CONNECT MOTOR CABLE Installation
11. CONNECT GENERATOR CABLE Installation
12. CONNECT FRAME WIRE Installation
13. CHECK HIGH VOLTAGE CABLE CONNECTION Installation
14. INSTALL INVERTER COVER Installation
15. INSTALL ENGINE ROOM MAIN WIRE Installation
16. INSTALL NO. 1 INVERTER BRACKET Installation
17. INSTALL SERVICE PLUG GRIP
Installation
18. ADD COOLANT (for Inverter) Coolant (for Inverter)
19. ADD COOLANT (for Engine) Coolant (for Engine)
20. INSPECT FOR COOLANT LEAK (for Inverter) Testing and Inspection
21. INSPECT FOR COOLANT LEAK (for Engine) Cooling System
22. INSTALL NO. 1 ENGINE UNDER COVER
23. INSTALL RADIATOR SUPPORT OPENING COVER Installation