ACTIVE AIR SHUTTER INSPECTION
id092300700600
Operation Inspection
1. Connect the M-MDS to the DLC-2.
2. Switch the main power ON (READY on).
3. Using the M-MDS simulation function, verify that the active air shutter operates when the AIRSHUT_POS_COMD is changed from 0 to 100%
(See PID/DATA MONITOR INSPECTION.)
DTC Inspection
1. Connect the M-MDS to the DLC-2.
2. Perform the DTC inspection for the pcm and verify if any DTCs related to the active air shutter is detected. (See DTC INSPECTION.)